Past projects

Project:

Extension to Primary School

Client:

Thrapston Primary School

Value:

£82,000

Programme:

18 weeks

Description:

A small extension to the existing primary school.

The construction itself was relatively traditional with brick cladding and concrete roof tiles to blend with the existing school.

Special Requirements:

This project presented a number of issues not least the proximity of young children to the works, and the lack of available space for storage.  This meant safety issues were of paramount importance and continuous dialogue with the school was essential.

The client and their team were delighted with the project and the minimal disruption to the daily activities of the school.

Primary School extension

Primary School extension